Order Lead Times
Guidelines for order leads, after receipt of order (ARO), are as follows:
Ceramic Fasteners |
| In Stock Products |
Ship same day if ordered before noon, following day if order received after noon. |
| Out of Stock Products |
7 - 10 business days |
Custom Ceramic Parts |
| For reorders that do not require post fire grinding |
4-6 weeks |
| For new parts requiring tooling but no post fire grinding |
6-8 weeks |
| For re-orders that require post fire grinding |
6-10 weeks |
| For new parts requiring tooling and post fire diamond grinding |
8-12 weeks |
- Actual lead time is dependent upon both the quantity ordered and the complexity of the ceramic component. The above guidelines are given to provide you with a general overview of the typical manufacturing times required for Ceramco to process your order.
|
| |